CONCRETE CALCULATOR FORMULA

  1. Determine how thick you want the concrete.
  2. Measure the length and width that you’d like to cover.
  3. Multiply the length by the width to determine square footage.
  4. Convert the thickness from inches to feet.
  5. Multiply the thickness in feet by the square footage to determine cubic feet.

What is the formula for calculating concrete quantity requirements?

Thus, the quantity of cement required for 1 cubic meter of concrete = 0.98/0.1345 = 7.29 bags of cement. The quantities of materials for 1 m3 of concrete production can be calculated as follows: The weight of cement required = 7.29 x 50 = 364.5 kg. Weight of fine aggregate (sand) = 1.5 x 364.5 = 546.75 kg.
Apr 1, 2015

How do you calculate reinforcement required on a slab?





Steps to calculate the Reinforcement required for Slab:-

  1. Deduct the cover for finding length of bar.
  2. Evaluate the length of the distribution bar.
  3. Calculate the Value of ‘D’ (Depth of slab- Top cover- Bottom cover)
  4. Find out the No. of Bars.
  5. Compute the Total wt of steel required for slab reinforcement.

Sep 10, 2017

How is slab design calculation?

Effective depth d= Span /((L/d)Basic x modification factor) For obtaining modification factor, the percentage of steel for slab can be assumed from 0.2 to 0.5%. The effective depth d of two way slabs can also be assumed using cl. 24.1,IS 456 provided short span is <3.5m and loading class is <3.5KN/m.
Nov 17, 2014

What is the best way to estimate the amount of concrete needed for a project?

Calculate the Project Volume



Multiply the area by the depth to arrive at volume. Example: 100 square feet of area multiplied by 0.5-foot depth is 50 cubic feet. So, to fill the coop’s form, you will need 50 cubic feet of wet, mixed concrete.
Apr 22, 2022

How do I calculate building quantities?





To calculate the quantities of materials, you need to multiply the total centre line length with breadth and depth of the construction. The centre line length will be reduced by half of breadth of every junction where the main wall is joined with the cross walls, partitions or verandah.
Sep 21, 2017

How many cubic meters of concrete do I need?

For a wall made of concrete the calculation is practically the same: height(ft) x width(ft) x length(ft). For example, to calculate the volume in cubic meters for a wall with a height of 2m, width of 20cm and length of 4m, you need to multiply 2 x 0.2 x 4, which equals 1.6 m3 (cubic meters).

What is minimum reinforcement in slab?

Minimum reinforcement is 0.12% for HYSD bars and 0.15% for mild steel bars. The diameter of bar generally used in slabs are: 6 mm, 8 mm, 10 mm, 12mm and 16mm. The maximum diameter of bar used in slab should not exceed 1/8 of the total thickness of slab.
Sep 25, 2013

How do you calculate reinforcement?

Method-2 : Reinforcement Estimation (Accurate Method):

  1. Calculation:
  2. Bar 1:
  3. Cutting Length = 4380 mm.
  4. Bar 2:
  5. Cutting Length = (2×200) + (4380) – (2 x 20 x 2) = 4700 mm.
  6. Bar 3:
  7. Cutting Length:
  8. No. of Stirrups: (4000/180) + 1 = 23.22 = 24.


Jan 13, 2015

How much steel is required for slab?

RCC Slab :



According to my calculation Steel is required for the RCC, the slab is ≈ 80 kg/m3. The total quantity of steel needed for 1 sq ft (0.0118 cubic meter) RCC slab is equal to = 80 × 0.0118 = 0.944 Kg. This means, 0.944 Kg of steel is needed per sq ft of 5-inch thick RCC slab.
Dec 18, 2021

What is the formula for concrete?

Concrete Calculator Formula For. figuring concrete yardage. The concrete calculator formula to figure cubic yards for a square or rectangle shaped concrete slab is (Length x Width x Thickness) / 27.

How do you bid a concrete slab?




Quote from Youtube video: So this section is 14 feet by 36. So i'll write that down 36 by 14.. And then this section here is 48 by 28 so i'll just write down my 48. By 28 and then this section here is the garage.

How much cement do I need for a 10×10 slab?

At 4″ thick, for a 10×10 slab, generally, you will need 1.23 cubic yards or 33 cubic feet or either 74- 60lb or 56-80lb bags of premixed concrete.

How do you calculate material requirements?

MRP system: how to calculate material requirements?

  1. Master Production Schedule (MPS) The production schedule (MPS) contains the quantity of each item to be produced within a particular time period. …
  2. Bill of Materials. …
  3. Current stock level.

Jan 31, 2019

How do you calculate construction material requirements?



Approximate cost on various work of material to complete the construction for 1000 ft 2

  1. Total Cost. = Builtup area × Approx cost per sq. ft. = 1000 × 1000. = 1000000.00 Rs. …
  2. Amount of Aggregate Required. = Builtup area × 0.608. = 1000 × 0.608. = 608.00 Ton. …
  3. Flooring. = Builtup area × 1.3. = 1000 × 1.3. = 1300.00 Sq.